Key functions of project manager:

  1. Solution of organizational, material and technical, financial issues, etc., appearing during the project.
  2. Determination of roles and responsibilities of project participants and project offices.
  3. Elaboration, approval and timely updating of project implementation plan.
  4. Monitoring of project implementation process, forecasting of deviations and timely measures on its removal.
  5. Coordination of communication between all project participants, interested party and partners.
  6. Project changes control; analysis of efficiency of project implementation stages, reflection of its results and totals.

Project manager is responsible for strategic management of project implementation.

Delegating functions:

* overall management of project implementation process;

* ensuring the allocation of necessary resources for project implementation, ensuring financing of work;

* review and approval of regulatory documents necessary for organization and realization of project;

* receipt and analysis of consolidated reports about project implementation process;

* management of changes in project basic parameters and problem solving.

Delegating privileges:

* approval of ideology and goals of a project;

* coordination of project curators assignment;

* approval of general plan and budget of a project;

* receiving of consolidated reports about project implementation process from a curator;

* adoption of policy decisions for critical changes affecting the deadlines, cost and quality of project results.

Curator is responsible for achieving of project goals within budget, in accordance with planned project deadlines and given quality level.

Delegating functions:

* formation of project offices and project management teams;

* planning, organization and control of work on project goals achievement with required quality, cost and at a given time;

* project resource allocation and organization of interaction between design offices during the process of implementation;

* organization of interaction and provision of communication links with other project participants;

* counting of actual costs of resources of project implementation;

* formation and provision of project report to Project manager;

Delegating privileges:

* task setting to project offices and its separate members, and monitoring of its performance;

* requirement from project offices to perform their role functions;

* confirmation or rejection of reports about actual costs of project performers;

* justification of need and request to Project Manager of additional resources for a project;

* appeal to Manager for support in case of need.